Re: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0


+1
agree with ali's comment

_______________________________________________________________________________________________________________
Mark Weitzel | STSM | IBM Software Group | Tivoli | Autonomic Computing | (919) 543 0625 | weitzelm@xxxxxxxxxx



Re: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0

Ali Mehregani to: Cosmos Dev
10/09/07 10:49 AM

Sent by: cosmos-dev-bounces@xxxxxxxxxxx

Please respond to Cosmos Dev <cosmos-dev@xxxxxxxxxxx>








+1
My only comment is to have the development block broken down into a design and implementation phase.

Thanks,
Ali Mehregani

On 10/4/07, Tania N Makins <tmakins@xxxxxxxxxx> wrote:

COSMOS Committers,


I have updated the proposal for schedule revisions, per our discussion during today's Community Call:
http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.2810.2F04.2F2007.29_-_Release_Milestones.

Summary of changes:
  • Moved Milestone 2 to the end of i9, which is March 7.  This milestone will be used for EclipseCon 2008.
  • Removed Milestone 3, which was originally scheduled for the end of i10.

Please review the latest proposal and post your vote by end of day tomorrow, October 5.



   Tania N. Makins
   Project Manager, AC Open Source Components
   IBM Software Group - RTP, NC
   Office: (919) 254-8430  T/L: 444-8430
   
tmakins@xxxxxxxxxx

_______________________________________________
cosmos-dev mailing list

cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev




--
Ali Mehregani
Test & Performance Tools Platform

http://www.eclipse.org/tptp _______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev


Back to the top