Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
Re: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0

+1
My only comment is to have the development block broken down into a design and implementation phase.

Thanks,
Ali Mehregani

On 10/4/07, Tania N Makins <tmakins@xxxxxxxxxx> wrote:

COSMOS Committers,

I have updated the proposal for schedule revisions, per our discussion during today's Community Call: http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.2810.2F04.2F2007.29_-_Release_Milestones.

Summary of changes:
  • Moved Milestone 2 to the end of i9, which is March 7.  This milestone will be used for EclipseCon 2008.
  • Removed Milestone 3, which was originally scheduled for the end of i10.

Please review the latest proposal and post your vote by end of day tomorrow, October 5.


    Tania N. Makins
    Project Manager, AC Open Source Components
    IBM Software Group - RTP, NC
    Office: (919) 254-8430  T/L: 444-8430
    tmakins@xxxxxxxxxx

_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev




--
Ali Mehregani
Test & Performance Tools Platform
http://www.eclipse.org/tptp

Back to the top