Re: [eclipse-dev] https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_16.php notes

> does not contain a single hint that we are in RC1

It says

27         Wed 18:00 EST                 Release Candidate 1 build        
29         Fri                                 Submit RC1 to release train

so, you are just wrong here. What's not clear here?

Yes, I need to update the status. But it looks like you know the plan and what's going on.

Dani



From:        Carsten Hammer <carsten.hammer@xxxxxxxxxxx>
To:        eclipse-dev@xxxxxxxxxxx
Date:        26.05.2020 15:05
Subject:        [EXTERNAL] [eclipse-dev] https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_16.phpnotes
Sent by:        eclipse-dev-bounces@xxxxxxxxxxx




Hi,
It looks like that the page https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_16.phpdoes not contain a single hint that we are in RC1. In contrast to this it clearly states we are "working towards m3“. The m3 release date is missing so that someone not familiar with the process must be thinking that 27 of May is meant.
I suggest to either point to https://www.eclipse.org/projects/project-plan.php?planor modify the freeze plan to contain the important/correct information.
Best regards,
Carsten_______________________________________________