The following components have no more planned work in 3.4.1:

* Platform & JDT Debug
* Ant
* API Tooling
* PDE UI

Darin Wright



Philippe P Mulet <philippe_mulet@xxxxxxxxxx> 
Sent by: platform-releng-dev-bounces@xxxxxxxxxxx
08/26/2008 09:52 AM
Please respond to
"Eclipse platform release engineering list." 
<platform-releng-dev@xxxxxxxxxxx>


To
"General development mailing list of the Eclipse project." 
<eclipse-dev@xxxxxxxxxxx>
cc
platform-releng-dev@xxxxxxxxxxx
Subject
[platform-releng-dev] Re: [eclipse-dev] 3.4.1 reminder







Teams, 

By reply to this note, could you please assess how much more work you are 
planning to release for 3.4.1 ? Having none left at this stage is actually 
a feature.
I am only aware of https://bugs.eclipse.org/bugs/show_bug.cgi?id=244631 
being investigated right now.

Just trying to get a sense of how much releng activity is ahead of us this 
week. 
Also remember to perform smoke testing as we agreed on during our 
retrospective discussions. 

Thanks! 

__________________ 


Thanks for the reminder John. 

Indeed, our plan for 3.4.1 is to be done by END OF THIS WEEK with 3.4.1 
RC1 (endgame plan will soon be posted at: 
http://www.eclipse.org/eclipse/development/freeze_plan_3_4_1.php). 
The RC1 material needs to be uploaded to Ganymede on Sept. 1st. 




John Arthorne <John_Arthorne@xxxxxxxxxx>   
Sent by: eclipse-dev-bounces@xxxxxxxxxxx 

08/21/2008 08:46 PM 

Please respond to 
"General development mailing list of the Eclipse project." 
<eclipse-dev@xxxxxxxxxxx>



To
eclipse-dev@xxxxxxxxxxx 
cc

Subject
[eclipse-dev] 3.4.1 reminder










This is just a reminder that according to [1] the RC1 date for Ganymede 
SR1 (3.4.1) is Monday September 1st, with the final release two weeks 
after that.  Unless we schedule extra maintenance builds next week, our 
next maintenance build (Aug 27th) will be our RC1 contribution. This means 
all bugs we plan to fix for 3.4.1 should be released by next Wednesday.  I 
noticed last year's 3.3.1 end-game started with an RC1 build on August 
15th, so be aware that the 3.4.1 end-game is much shorter. 

[1] - 
http://wiki.eclipse.org/Ganymede#Coordinated_Service_Releases_.28Proposed.29 
_______________________________________________ 
eclipse-dev mailing list 
eclipse-dev@xxxxxxxxxxx 
To change your delivery options, retrieve your password, or unsubscribe 
from this list, visit 
https://dev.eclipse.org/mailman/listinfo/eclipse-dev 
  


Sauf indication contraire ci-dessus:/ Unless stated otherwise above: 
Compagnie IBM France 
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 
Courbevoie 
RCS Nanterre 552 118 465 
Forme Sociale : S.A.S. 
Capital Social : 542.737.118 euros 
SIREN/SIRET : 552 118 465 02430 


_______________________________________________
eclipse-dev mailing list
eclipse-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe 
from this list, visit
https://dev.eclipse.org/mailman/listinfo/eclipse-dev 


Sauf indication contraire ci-dessus:/ Unless stated otherwise above:
Compagnie IBM France
Siège Social : Tour Descartes, 2, avenue Gambetta, La Défense 5, 92400 
Courbevoie
RCS Nanterre 552 118 465
Forme Sociale : S.A.S.
Capital Social : 542.737.118 euros
SIREN/SIRET : 552 118 465 02430
_______________________________________________
platform-releng-dev mailing list
platform-releng-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/platform-releng-dev




Back to the top