We are good to finish the e2e testing and
some ER validation using an ITC machine by 23rd November 2007. For
i7 we are certifying the build and the e2e tests in Windows platform (XP SP2).
Regards
Shivashankari
From: Mohsin, Jimmy
Sent: Thursday, 22 November 2007
1:23 PM
To: Hubert H Leung; N,
Shivashankari; Mark D Weitzel
Cc: Cosmos Dev; Devine, John T;
Simmonds, Martin; Stratton, Paul; Sheldon Lee-Loy; Muldoon, William H
Subject: RE: Meeting on Thursday
to go over i7 end-to-end test case
Hubert / Sheldon,
Thanks a trillion for turning around the
wiki so QUICKLY…. This answers the following question: what are the
E2E tests for i7….
Shivvy,
Please review section 3 carefully on http://wiki.eclipse.org/Installing_i7_Build
that Hubert / Sheldon just published; if we complete these E2E tests, the i7
build is good. This will cover the i7 ERs that you have been looking at..
Seems the only major items we need to hit
in the 8AM meetings are:
·
Item 4 below in my email below, i.e. does
Shivvy use an ITC machine or use a remote machine due to timeframe
considerations for i7? That said, a local ITC machine will be needed
eventually (for i8 and onwards).
·
Even though this is a given, Hubert and
Sheldon can confirm that the E2E tests they have documented on the Wiki above
will cover all the i7 ERs.
·
Can you complete this E2E tests by Monday
AM ?
Paul,
Anything you wish to add?
Thanks,
Jimmy Mohsin
Cell +1-609-635-1703
From: Hubert H Leung [mailto:hkyleung@xxxxxxxxxx]
Sent: Wednesday, November 21, 2007
6:28 PM
To: Mohsin, Jimmy
Cc: Cosmos Dev; Devine, John T;
Simmonds, Martin; Loesch, Mary-Joelle; Stratton, Paul; Sheldon Lee-Loy; N,
Shivashankari; Muldoon, William H
Subject: Re: Meeting on Thursday
to go over i7 end-to-end test case
I have updated the wiki page at
http://wiki.eclipse.org/Installing_i7_Build. I have included instructions
on how to run an end-to-end testcase. Please consider this "test
case" as the end-to-end test case for i7. If Shivvy can reproduce
the steps on her computer, then we can declare the end-to-end integration test
for i7 to be successful.
Shivvy,
please re-download all packages linked from the download section of the wiki
page. I made some minor changes to the build today. Please also try
to follow my instructions to install the build from scratch. That is,
remove the files you installed from previous attemps, and also remove the two
registry XML files. You should be able to run the build on any computer.
You don't have to do the testing remotely on a computer in UK or US.
I hope you can try out the install before the meeting.
Thanks,
_________________________
Hubert Leung
IBM Toronto Lab
hkyleung@xxxxxxxxxx
905-413-3382
"Mohsin, Jimmy" <Jimmy.Mohsin@xxxxxx>
11/21/2007
02:23 PM
|
To
|
"Stratton, Paul" <Paul.Stratton@xxxxxx>,
"Simmonds, Martin" <Martin.Simmonds@xxxxxx>, "N,
Shivashankari" <Shivashankari.N@xxxxxx>, "Devine, John
T" <John.Devine@xxxxxx>, "Cosmos Dev" <cosmos-dev@xxxxxxxxxxx>,
"Muldoon, William H" <William.Muldoon@xxxxxx>
|
cc
|
Sheldon Lee-Loy/Toronto/IBM@IBMCA, Hubert H
Leung/Toronto/IBM@IBMCA, "Loesch, Mary-Joelle"
<Mary-Joelle.Loesch@xxxxxx>
|
Subject
|
Meeting on Thursday to go over i7 end-to-end test case
|
|
Paul,
Just had a call with Hubert and Sheldon…
Some comments on the i7 e2e testing that Shivvy is trying to get
going…
1. The completion date for
the e2e test is November 23; however, this effectively
means November 26 AM.
2. Hubert and Sheldon will
verify & validate the list of ERs Shivvy is
looking at for i7 (ACTION: Shivvy, please
do a reply all and send out that list PRIOR to this meeting tomorrow).
3. Hubert and Sheldon have
created a Wiki page that will address the following:
a. Based on our conversation
now, they will define some SIMPLE criteria for QA to say that the end to
end i7 test is complete. This is the info that Shivvy will use to say
that the i7 build is good. Please note the e2e testing will NOT
necessarily be testing each i7 ER one by one; it will be a SIMPLER overall
testing sequence that Hubert / Sheldon will define.
b. The info needed to ensure
that one has all the components needed to test the build
c. Potentially some manual
tests
that Shivvy needs to do with i7
4. Given the timing,
we still
need to determine if Shivvy should do the i7 build sign-off on a machine
in
India; OR if she should do this remotely on a US / UK machine. If the latter is the
case, which machine does Shivvy use? This item
needs to be closed off in this meeting.
5. As part of this exercise,
Shivvy ALSO needs to document the issues that she sees in the current
build
process and how hand-off-to-QA is done. For i8, we CLEARLY need to
resolve
this situation. This is a FUNDAMENTAL quality issue that Shivvy needs to clearly
understand, define and ensure that it is addressed in i8. This
has implications for Adoptability, which is a KEY metric for M2.
Thanks,
Jimmy Mohsin
Cell +1-609-635-1703
-----Original
Appointment-----
From: Stratton, Paul
Sent: Wednesday, November 21, 2007 12:57 PM
To: Simmonds, Martin; N, Shivashankari; Stratton, Paul
Cc: Mohsin, Jimmy
Subject: Meeting on Thursday to go over end-to-end test case
When: Thursday, November 22, 2007 8:00 AM-9:00 AM (GMT-05:00)
Eastern Time (US & Canada).
Where:
When:
22 November 2007 13:00-14:00 (GMT) Greenwich Mean Time : Dublin,
Edinburgh, Lisbon,
London.
*~*~*~*~*~*~*~*~*~*
I
have scheduled a meeting on Thursday 8am EST to go over the end-to-end test
case. The main purpose is to help Shivvy run the i7 build, but all are welcome.
I have set up an e-meeting for this meeting so we share desktops.
Here
is the meeting information:
November
22 (Thursday)
8:00
am EST (GMT -5)
Phone
conference number:
Toll-free
Dial-in: 1-866-245-5059
Local
Dial-in: 416-343-2607
Global
Dial-in:800-4444-1010
Conference
ID: 2771920
JOIN
THE WEB CONFERENCE
1)
Join the conference up to 20 minutes prior to 8:00 AM at 11/22/2007
2)
Direct your web browser to the following URL: http://www.ibm.com/collaboration/webconferences/center/meetingdetails.jsp?meetingId=4BE66EDB0B7E0DF1D2B53F04D6B4B83F
3)
When prompted, enter the web conference password: cosmos4you
WEB
CONFERENCE DETAILS:
Conference
URL: http://www.ibm.com/collaboration/webconferences/center/meetingdetails.jsp?meetingId=4BE66EDB0B7E0DF1D2B53F04D6B4B83F
Password:
cosmos4you
Conference
name: end-to-end testing
Start
time: 11/22/2007 8:00 AM (GMT -5)
Duration:
0d 2h 00m
_________________________
Hubert
Leung
IBM
Toronto Lab
hkyleung@xxxxxxxxxx
905-413-3382