[technology-pmc] EPF project - release review
|
Hi,
As detailed on email below, the Eclipse
Process Framework (EPF) team would like to proceed with a release review
on August 13.
PMC, please provide your permission
for us to conduct this review.
We will have a first version of IP Log
and slide deck available by Tuesday, August 5, 12PM PDT, so you can provide
your initial feedback.
The final version should be available
by COB Wednesday, August 6.
Please, let us know if we need anything
else in order to be on schedule for the review on the 13th.
Thank you very much.
Ricardo Balduino, EPF Committer
___________________________________________
Ricardo Balduino | Sr. Software Engineer
IBM Rational | SolAr CoP team | RUP SIG lead
Anne Jacko <emo@xxxxxxxxxxx>
07/31/2008 02:38 PM
|
To
| Ricardo Balduino/Cupertino/IBM@IBMUS
|
cc
| Per Kroll/Cupertino/IBM@IBMUS
|
Subject
| Re: [eclipse.org-committers] Eclipse
project reviews |
|
Hi Ricardo,
There is a review call scheduled for Wednesday, August
13, at 8am PDT. If you can have everything in place by Wednesday, August
6, then you could be on that review call. This is what you need to have:
1. Permission from your PMC to have the review (forwarded
email to emo is fine)
2. An approved IP Log
3. The slides for the review in final form (meaning that
you've sent them in earlier and we've looked at them and said they're OK)
To start the IP Log review process, I recommend that you
send email ASAP to emo-ip-team@xxxxxxxxxxx
(please cc emo@) and tell them you need the review complete before August
6.
Just let me now if you think you can get
this together in time, and I'll go ahead and put you on the schedule. Thanks!
Anne Jacko
emo@xxxxxxxxxxx
On Jul 31, 2008, at 2:12 PM, Ricardo Balduino wrote:
Hi Anne,
We need to schedule a release review for the EPF project (release planned
for Aug 22).
When is there availability for this review, and when would you expect to
have the slides and project log?
Thank you,
Ricardo Balduino
EPF Committer.
___________________________________________
Ricardo Balduino | Sr. Software Engineer
IBM Rational | SolAr CoP team | RUP SIG lead
Hello all,
Below is the schedule of upcoming reviews. Thanks.
Project Reviews
Reviews are held on a conference call for
Eclipse
Members. Members (and committers
are members) are directed to the MyFoundation
portal for the call-in information.
If you do not have access to the portal, send email
to EMO to request the call
information.
Anne Jacko
emo@xxxxxxxxxxx
_______________________________________________
eclipse.org-committers mailing list
eclipse.org-committers@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/eclipse.org-committers
IMPORTANT: Membership in this list is generated by processes internal to
the Eclipse Foundation. To be permanently removed from this list,
you must contact emo@xxxxxxxxxxx
to request removal.