Next week is the milestone week for 4.18 M3.
Monday: Last day of development (and even then, no "big changes").
After Monday 18:00 ET, no feature work or unrelated fixes are allowed -- only regression fixes.
Tuesday: All-day test pass. Nobody should develop or fix anything. Literally spend the entire day testing.
Wednesday:
Fix day with a focus on fixing regressions found during the test day
(Tuesday). No unrelated fixes. Review and thoroughly test all commits.
- The last Wednesday build is the release candidate every team signs off on Thursday.
- The "New and Noteworthy" entries are due on Wednesday evening:
Git repo: ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
Gerrit: ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
Live website: https://www.eclipse.org/eclipse/news/4.18/
Thursday:
Sign-off after re-testing, or at least confirming no changes have been
made to your component's code since the last time the component was
tested well.
Friday: Build is officially declared and made available.
-
The master branch stays closed until the milestone is officially
released. (That is, it is not enough that your component has signed
off.)
Regards,
--
Alexander Kurtakov
Red Hat Eclipse Team