Re: [jwt-dev] JWT Project plan
|
Answering the question myself : from what's at
http://www.google.fr/search?q=ganymede+release+review ,
I'd say JWT's Galileo release needs a normal release review with slides.
I'd say to do it as soon as possible. Mickaël proposes not long after M7
(6 May) so there won't be any feature changes afterwards, which suits
me. Then we'd have the right to release a 0.6 build with the same
feature set in Galileo.
What do you think ?
More about the project plan : other projects include all milestones and
RC of the simultaneous releases, which we could also do next year.
Regards,
Marc
Marc Dutoo a écrit :
Hi Florian
0.6 was to meant be "for integrators" (extensibility like aspects...),
and 0.7 "SOA" (calling webservices...).
Sure jBoss and Bull's roadmap have been delayed. But Scarbo builds on
JWT on both accounts. I guess the reason we didn't *need* a release is
because the build process now makes it really easy to build and use
stable builds (thanks Mickaël ;). Though the reason we'd *want* more
releases is to get spoken of more ;)
But right now 0.6 being Galileo is OK with me. I guess it should need
a release review, but I don't know actually. I'll ask right now to Anne.
Regards,
Marc
Florian Lautenbacher a écrit :
Hi guys,
I just realized that our current project plan (visible at
http://www.eclipse.org/projects/project_summary.php?projectid=technology.jwt)
shows that we have a tentative 0.6 release out *yesterday*.
When we worked on that project plan, we had the Bull and JBoss
release in mind that wanted to build on JWT which is why we wanted to
have a release prior to Galileo they can use. As JBoss won't build
upon JWT for their release this year (but probably next year) and
there are some restructurings at Bull, this necessity is not the case
anymore.
So I would like to discuss with you, how we shall adapt the current
project plan: do we want to have another JWT release prior to Galileo
or shall the Galileo release be our next one (then with version 0.6)?
Version 0.7 is currently planned for 13th of July which wouldn't make
sense with a 0.6 together with Galileo at the end of June. As we
discussed with our mentor John and the technology PMC Wayne, it would
make sense to have a graduation release sometime after Galileo,
probably in autumn or beginning of winter 2009 (once the community is
getting bigger which we are on a good way in my opinion).
My idea now would be to focus on the Galileo release at the moment
which would then be version 0.6.0 (we need to create some release
slides and all other information material for Galileo nevertheless,
don't we?) and either have another 0.7 in autumn or already a 1.0.
What do you think about this? John, any advice from your side here?
Have a nice weekend and best regards,
Florian
------------------------------------------------------------------------
_______________________________________________
jwt-dev mailing list
jwt-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/jwt-dev