Hi all,
We are scheduled to promote and contribute 4.19 RC1 to the simrel on Friday the 28th.
Don't forget to consult the endgame plan regarding release candidates:
https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_20.php
Here is the schedule:
| 26 | Wed 18:00 New York time | | API and feature freeze | |
| 26 | Wed 18:00 New York time | | Release Candidate 1 build | |
| 28 | Fri | | Submit RC1 to release train | |
Please note the following excerpt from the freeze plan
RC1
All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.
Please Note: Master branch is open for 4.20 RC1 contributions.
Thanks and Regards,
Sravan
Sravan Kumar Lakkimsetti
IBM India Pvt Ltd,
Embassy Golf Links Business Park, C Block,
Off Indiranagar-Kormangla Inner Ring Road,
Bangalore - 560071, India