Re: [ejb-dev] Please give your estimate of when you will complete your tasks for Jakarta EE 9.1 TCKs ...
|
From an EJB perspective we don't have a standalone TCK or independent compatible implementation. Our timeline is dictated by the Platform.
We do have two platform TCK items to complete:
- Signature tests for javax.rmi.PortableRemoteObject, required for EJB 2.x optional group
- Ensure there is an optional group for EJB 2.x views separate from EntityBeans optional group
I suspect it will take 2 weeks at our current pace.
--
David Blevins
http://twitter.com/dblevins
http://www.tomitribe.com
> On Mar 19, 2021, at 6:43 AM, Scott Marlow <smarlow@xxxxxxxxxx> wrote:
>
> Hi,
>
> On March 23, I will give the Jakarta EE Platform team a schedule update on when the Jakarta EE Platform TCK changes for 9.1 will be complete. Obviously, we need to be passing all optional/required TCKs tests before releasing 9.1 final (including BV, CDI, JAF, MAIL TCKs).
>
> My ask for you is to let me know before March 23 your estimate of when you will have completed your TCK tasks for EE 9.1.
>
> Thanks,
> Scott
>