Folks,
most of Web Services and portions of J2EE tools will not be in the 2/10 I-build. There are a few final bits of integration work being done now, and which will be introduced into HEAD in the next day or two. Everything should be in the following week's (2/17) build.

Web services function in M3 will consist mainly of wizards for building, deploying and testing Apache Axis 1.1 Java (not EJB) Web services (bottom-up and top-down) and clients on various Apache Tomcat servers. With a bit of luck, M3 may also include the infamous Web Services Explorer. For more information please see the WST Web Services [1] and JST Web Services [2] M3 milestone plans.

[1] http://www.eclipse.org/webtools/wst/components/ws/M3/milestone_plan.html
[2] http://www.eclipse.org/webtools/jst/components/ws/M3/milestone_plan.html

Cheers - CB.

Chris Brealey
Rational Studio Java Web Services, IBM Canada Ltd.
D3-275, D3/ENX/8200/MKM, 8200 Warden Avenue, Markham, Ontario, Canada, L6G 1C7
cbrealey@xxxxxxxxxx, 905.413.6038, tieline:969.6038, fax:905.413.4920



David M Williams <david_williams@xxxxxxxxxx>
Sent by: wtp-dev-admin@xxxxxxxxxxx

02/08/2005 10:54 PM

Please respond to
wtp-dev

To
wtp-dev@xxxxxxxxxxx
cc
Subject
[wtp-dev] Upcoming important dates for WTP M3






Its that time of the cycle again, so thought I would explicitly summarize what's been

discussed and written in many different talks and notes and plans.


2/10 - Thursday - regular I-build ... most teams are planing to have all planned major

       function "in the build" by this I-build

       (its no show-stopper if not there, but, if not there, a note to this list would

       help keep everyone aware of status and last minute changes still coming).


2/11 - Friday. move up to latest Eclipse M5 I-build, and "all the latest" of GEF,

       EMF/XSDInfoset, and JEM.

       (early peeks indicate there will be roughly 42 compile errors when we first move

       up, so several teams have some work to do).


2/18 - Friday, Final Test Plans and new mini-tutorials for new function for this

       Milestone, from each component team (please update previous tutorials where

       changed, include some regression testing on previous function,

       but focus on new function just added -- and remember, no need to wait until this

       final deadline if you can provide earlier!).


2/18 - Friday - Final Eclipse M5 due


2/19 - Saturday, move up to final M5 and pre-reqs (can build team can work weekend?,

       if so, I suggest one person from each component team be available on weekend to

       keep them company, and sanity test the results, to be sure there's

       no serious issues that would prevent further final testing during the week)


2/21 - 2/-25  Monday through Friday. Milestone shutdown testing, serious bugs fixed


2/25 - Friday - final M3 build declared and promoted to web site


2/28 - EclipseCon -- I've listed this fast-approaching date here to emphasize the

       importance of stability for those preparing demos, etc.



Please let me know if I've missed (or misunderstood) anything.