[platform-releng-dev] Next week is our M5 stabilization week ...

Our Luna, M5 +0 is due 1/24, which means beginning Sunday, 1/19, 8 PM (Eastern), I'll turn off "N-builds", and we'll have I builds only, twice a day, until Wednesday, 8 PM, with Thursday 1/23 being "sign off" day, for our M5 contribution. Please plan accordingly.  

While our "M-build" of that week does not _have_ to be contributed for Kepler SR2, we should not skip it, since we will be ramping down for SR2. Thus, I've moved it's time to 10 AM, instead of 8 AM, for that one day only.

I have updated our build schedule to reflect these busy days.