We've had some good
news on the IP due diligence front and it's time to
think about next steps.
My next best window of opportunity for a release review
is February 17. I think that we can reasonably make this
target. We'll have to have the pieces in place by Feb
10.
We'll task the project teams with submitting their IP
Logs for review by the IP Team and assembling review
documentation. I've just restarted the Git repository
harvester process with some fixes, so we'll target
running the IP Logs on Monday.
Review documentation is entered into a release record in
the PMI. I look for a description of the release that I
can understand. There are other fields that may be
filled if the project team and PMI feel that there's
value in providing information there.
This whole process shouldn't take more than about 30
minutes of the project lead's time.
The process is described in gory detail in the handbook.
https://www.eclipse.org/projects/handbook/locationtech.html#release
Does it make sense to schedule a Hangout to discuss for
early next week?
I'm available Monday 1-5 or Tuesday 10-12 (eastern
timezone)
Wayne
--
Wayne Beaton
@waynebeaton
The Eclipse Foundation