Hi everyone,
Let's try to plan our releases during Luna . Here is what I have in mind -
feel free to say I'm nuts and propose a better one :):
* 2.0.1 release - our Kepler SR1 (August 28th?) - strictly bug fixing - no
API breakage.
* 2.1 - new feature release (Late November) - new features and new API
allowed but no breakage of the 2.0 API.
* 2.1.1(if needed) - our Kepler SR2(January 22th?) - bug fixes on top of 2.1,
no API breakage.

Once 2.1 is released, master will be targeting Luna (aka our 3.0 release) -
API breakage, new features, etc allowed.
After talking to Jeff, he proposed making all the releases new features aka 2.1, 2.2 and 2.3 at pretty much same time as the initial proposal.
Lttng devs, is this what you were asking for in the other thread?
Hi Alexander,

You are proposing following schedule or did I misunderstand?

2.1 release - Kepler SR1 (09/27/2013) - bug fixes and *new features*
2.2 release - Kepler SR2 (02/28/2014) - bug fixes and *new features*
3.0 release - Luna - bug fixes, new features and *API breakage*

* http://wiki.eclipse.org/Kepler/Simultaneous_Release_Plan#Schedule

- Wainer


Alexander Kurtakov
Red Hat Eclipse team

Any thoughts?

Alexander Kurtakov
Red Hat Eclipse team

_______________________________________________
linuxtools-dev mailing list
linuxtools-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/linuxtools-dev

_______________________________________________
linuxtools-dev mailing list
linuxtools-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/linuxtools-dev




Back to the top