Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
Re: [iot-pmc] Eclipse Kura v3.1.0 Release

Hi Dave,

The bug used to track the release is https://bugs.eclipse.org/bugs/show_bug.cgi?id=521275
Regarding the CQs:
  • 13853 and 13796 have ongoing discussions between the Kura team and IP team.
  • 14003, 13854, 13825 either lacked PMC approval (sorry about that), or are already in IP’s team hands

I would suggest you contact the IP team and share with them this list of 5 CQs so that they are aware you need them resolved to move forward with submitting your IP Log and doing your 3.1.0 release.

Thanks,
Benjamin -



Le 22 août 2017 à 21:22, Woodard, David <David.Woodard@xxxxxxxxxxxx> a écrit :

Hello,
 
I wanted to confirm a few things for the next release of Eclipse Kura.
 
·         Are we still set for a review date of September 20th? I couldn’t find this documented anywhere on the project page, maybe I am just not seeing it.
·         Usually there is a bug created to track the release (I think by the PMC?), has that happened?
·         We are tracking the below CQs for this release. I believe they are all waiting Eclipse Legal or PMC. Would it be possible to get these updated in the next week or two?
 
 
Thanks,
--Dave
 
 
 
 
From: <stephanie.swart@xxxxxxxxxxxxxxxxxxxxxx> on behalf of EMO EMO <emo@xxxxxxxxxxxxxxxxxxxxxx>
Date: Wednesday, July 19, 2017 at 10:06
To: "Woodard, David" <david.woodard@xxxxxxxxxxxx>
Subject: Re: [iot-pmc] Eclipse Kura v3.1.0 Release
 
Hi David, 
 
I have updated the release review date to September 20, 2017. Please let me know if anything changes.
 
Thank-you,
Stephanie
 
On Wed, Jul 19, 2017 at 12:03 PM, Woodard, David <david.woodard@xxxxxxxxxxxx> wrote:

Hi Stephanie,

 

Thanks for letting us know. Let's schedule for September 20th.

 

Thanks,

--Dave

 


From: stephanie.swart@xxxxxxxxxxxxxxxxxxxxxx <stephanie.swart@xxxxxxxxxxxxxxxxxxxxxx> on behalf of EMO EMO <emo@xxxxxxxxxxxxxxxxxxxxxx>
Sent: Wednesday, July 19, 2017 7:08:04 AM
To: Woodard, David
Subject: Re: [iot-pmc] Eclipse Kura v3.1.0 Release
 
Hi David, 
 
Thank you for the heads up on the upcoming release.
 
I would like to point out that we (the EMO) do release reviews on the first and third Wednesday of every month, therefore the review must fall on either September 20th or October 4th. 
Please let me know which one of these dates you'd prefer and I can make the necessary changes.
 
 
Thank-you,
Stephanie
 
On Tue, Jul 18, 2017 at 7:34 PM, Woodard, David <david.woodard@xxxxxxxxxxxx> wrote:

Hello,

 

The Eclipse Kura team has scheduled a new release of Eclipse Kura (v3.1.0). I have requested a review date of September 27. It may be a bit early for sending this email, but I know October is a busy time for the Eclipse Foundation so I wanted to get on your radar early. The review information can be found here [1], please let me know if you see any potential issues at this point.

 

[1] https://projects.eclipse.org/projects/iot.kura/releases/3.1.0

 

Thanks,

David Woodard

Eclipse Kura Project Lead


_______________________________________________
iot-pmc mailing list
iot-pmc@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://dev.eclipse.org/mailman/listinfo/iot-pmc



 
-- 
The Eclipse Management Organization
Eclipse Foundation


 
-- 
The Eclipse Management Organization
Eclipse Foundation
_______________________________________________
iot-pmc mailing list
iot-pmc@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit