[equinox-dev] 4.7.2 RC3 Schedule

Hi,

 

We have scheduled 4.7.2 RC3 for Nov 24, 2017

 

Here is the end game plan http://www.eclipse.org/eclipse/development/plans/freeze_plan_4_7_2.php

 

Please note:  All fixes submitted to RC3 must have a PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). Ensure that all feature/plugin versions have been consistently incremented when needed

 

Here is the schedule(all times in Eastern time zone US):

Nov 20, 2017 5 PM        Checkpoint1 build

Nov 22, 2017 4 AM        Checkpoint2 build

Nov 22, 2017 5 PM        RC3 Candidate build

Nov 23, 2017                 1-day test pass against RC3 and sign-off

Nov 24, 2017                 Promotion (make build available on download page and contribute to simrel)

 

Thanks and Regards,

Sravan

 

Sravan Kumar Lakkimsetti

IBM India Pvt Ltd,

Embassy Golf Links Business Park, D Block,

Off Indiranagar-Kormangla Inner Ring Road,

Bangalore - 560071, India

Phone: 91-80-41776858



Back to the top