Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
[dsdp-tm-dev] FW: DSDP-TM requests delaying our M6 drop by 4 days

OK,
 
I have asked on the planning council and cross project lists, see below.
Thanks for your replies.
 
Cheers,
--
Martin Oberhuber, Senior Member of Technical Staff, Wind River
Target Management Project Lead, DSDP PMC Member
http://www.eclipse.org/dsdp/tm
 
 


From: Oberhuber, Martin
Sent: Freitag, 04. April 2008 15:16
To: 'Cross project issues'; 'eclipse.org-planning-council'
Subject: DSDP-TM requests delaying our M6 drop by 4 days

Dear all,
 
thanks to the truly awsome API Tooling in Eclipse 3.4M6, we have
detected several API Leakage problems in the Target Management
Project, that we'd like to address in a clean manner before our
M6 API Freeze.
 
This unexpected extra work has delayed our M6 test plan, so
we'd like to delay our M6 Ganymede Drop by 4 days from
Mon Apr 7 (+2) to  Fri Apr 11 (EPP).
 
I'm not aware of any downstream consumers that we currently have,
so I'd hope that this is in order. Still I'd like to get your replies if
there are any concerns.
 
Note that I have contributed a preview of our TM M6 drop today
already, and will be refining it again on Monday, so hopefully
our API's shouldn't change any more after the initially expected
drop date. Still I'd like to get the extra 4 days of testing.
 
Any thoughts or concerns?
 
Thanks,
--
Martin Oberhuber, Senior Member of Technical Staff, Wind River
Target Management Project Lead, DSDP PMC Member
http://www.eclipse.org/dsdp/tm
 
 

Back to the top