RE: [cross-project-issues-dev] GMF RC6 is ready
|
The intent was certainly to have "all ready"
by 5:00 PM today ... 30 minutes and counting :)
Wednesday 6/28
[edit]
by 17:00 EDT, at the latest
- projects have prepared zips downloads and all update site
files (again, offline -- just have them ready to go).
- projects ensure update jars are in their "temporary"
locations, as listed in the feature-*.xml files
- projects ensured callisto.tools feature-*.xml files all
up to date
- callisto 'staging' will be created to verify all are accurate,
and ready to be copied to releases area
"Mike Milinkovich"
<mike.milinkovich@xxxxxxxxxxx>
Sent by: cross-project-issues-dev-bounces@xxxxxxxxxxx
06/28/2006 04:14 PM
Please respond to
mike.milinkovich@xxxxxxxxxxx; Please respond to
Cross project issues <cross-project-issues-dev@xxxxxxxxxxx> |
|
To
| "'Cross project issues'" <cross-project-issues-dev@xxxxxxxxxxx>
|
cc
|
|
Subject
| RE: [cross-project-issues-dev] GMF RC6
is ready |
|
Max,
But to be part of Callisto, don't
you need to make those renamed bits *today*, not tomorrow?
From: cross-project-issues-dev-bounces@xxxxxxxxxxx
[mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of Max
Feldman
Sent: June 28, 2006 4:06 PM
To: Cross project issues
Subject: Re: [cross-project-issues-dev] GMF RC6 is ready
Steven,
Not sure I got what your concern is, but yes, what we are going
to do is to just rename GMF RC6 bits to 1.0 Release and publish/announce
them tomorrow as the GMF 1.0 release in case there are no serious problems
with us or with Callisto compilation.
So.. I guess we're on the same page..
Regards,
Max
Steven Wasleski wrote:
Max and perhaps submitters from other projects,
It is my understanding from the "Final Daze" shutdown plan (http://wiki.eclipse.org/index.php/Callisto_Final_Daze)
that the bits being submitted to Callisto today are suppose to be the final
GM bits and not another RC that will later be renamed to be the release
build (it is my understanding the GMF intends to rename RC6 to the release
build). I believe the intention is that today's submissions are the last
ones. I know that some of the projects, like WTP, intend to submit their
renamed release build and I believe everyone else should be as well.
Am I or are others misreading something here? It seems to me that another
round of submissions would expose the Callisto schedule.
Thanks,
Steve Wasleski
IES Technical Lead
Max
Feldman <max.feldman@xxxxxxxxxxx>
Hi,
feature-gmf.xml points at the temporary location with GMF RC6 bits.
Best regards,
Max
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev