[cosmos-dev] Committers/contributors should know: how-to for the remainder of v1.1 iteration 1
|
Hi folks,
This is the last week of development for iteration 1. On Wednesday we will
build a candidate build and every team must run a sanity test on this
driver to ensure that everything that you've checked in so far is good for
the official test pass, which starts Monday next week. Due to the
holidays, the test pass for iteration 1 will span 3 weeks instead of the
standard 2 weeks (Dec 22 to Jan 09).
Each team must state the results of its tests this week in the wiki page
showing this week's test state: http://wiki.eclipse.org/COSMOS_v1.1_I1w5
Only when all teams have reported status will we know if we're good to go
with the test pass or not.
All status during the test pass of iteration 1 must be entered in this
wiki page: http://wiki.eclipse.org/COSMOS_v1.1_I1_Test
This iteration we are producing an iteration driver, not a milestone
driver, and thus the test pass is to ensure that the iteration driver is
stable. We will not advertise this driver because Eclipse allows us to
advertise only Milestone and Release drivers, but it is possible that an
early adopter will pick up this driver and it is expected, in accordance
with Agile practices, that the driver is usable.
You can find links to all of the iteration plans and test pages in the
COSMOS Release Plan: http://wiki.eclipse.org/Cosmos_Release_Plan#Features
MILESTONE DURATION START DATE END DATE DESCRIPTION
Iteration 1 8 weeks Nov-17-2009 Jan-09-2009 Enhancements
i1 Development 5 weeks Nov-17-2009 Dec-19-2009 Development &
bug fixes
i1 Testing 3 weeks Dec-22-2009 Jan-09-2009 Validation
Testing
Iteration 2 6 weeks Jan-12-2009 Feb-20-2009 Enhancements
i2 Development 4 weeks Jan-12-2009 Feb-06-2009 Development &
bug fixes
i2 Testing 2 weeks Feb-09-2009 Feb-20-2009 Validation
Testing
Iteration 3 6 weeks Feb-23-3009 Apr-03-2009 Stabilize
i3 Development 4 weeks Feb-23-2009 Mar-20-2009 Development &
bug fixes
i3 Testing 2 weeks Mar-23-2009 Apr-03-2009 Validation
Testing
Milestone driver 1 day Apr-03-2009 Apr-03-2009
Available for POCs
Iteration 4 6 weeks Apr-06-2009 May-15-2009 Enhancements
i4 Development 4 weeks Apr-06-2009 May-01-2009 Development &
bug fixes
i4 Testing 2 weeks May-04-2009 May-15-2009 Validation
Testing
Iteration 5 6 weeks May-18-2009 June-26-2009 Stabilize
i5 Development 4 weeks May-18-2009 June-12-2009 Development
& bug fixes
i5 Testing 2 weeks June-15-2009 June-26-2009 Validation
Testing
COSMOS 1.1 availability 1 day June-26-2009 June-26-2009 GA
Release
Ruth Lee
IBM Toronto Lab
ruthdaly@xxxxxxxxxx