Re: [cosmos-dev] i9 QA Phase Execution - Schedule
|
Srinivas,
I had thought that QA was not doing
#2 in the primary tasks; i.e. until yesterday you were only doing #1, and
added #3 on request.
David
"Doma, Srinivas Reddy"
<SrinivasReddy.Doma@xxxxxx>
Sent by: cosmos-dev-bounces@xxxxxxxxxxx
02/28/2008 09:52 AM
Please respond to
Cosmos Dev <cosmos-dev@xxxxxxxxxxx> |
|
To
| "Cosmos Dev" <cosmos-dev@xxxxxxxxxxx>
|
cc
| "Adivishnu, Kishore" <Kishore.Adivishnu@xxxxxx>
|
Subject
| [cosmos-dev] i9 QA Phase Execution -
Schedule |
|
Hi,
As per yesterday’s
Architecture Call discussions, we have revisited
i9 QA Tasks and included
Data Visualization
TPTP Manual Tests
into our
schedule which is listed below.
QA Primary Tasks (28 February, 2008
– 07
March, 2008)
1. E2E
testing on Windows XP, 2003 and Red Hat Enterprise Linux Server 5.0 (http://wiki.eclipse.org/COSMOS_DEMO_i9
)
2. i9
ERs (17 ERs) – JUnits/Manual
Tests inspection (http://wiki.eclipse.org/Cosmos1.0Features#Iteration_9_Enhancements)
3. Data
Visualization TPTP Manual Tests Execution (DataVisualization.UI.Component.Widget.testsuite
/ UI.Reports.testsuite)
QA
Secondary Tasks (10 March,
2008
–
14
March, 2008)
1. Execution
of i9 supplement e2e tests from QA.
2. Basic
operational efficiency tests (limited performance tests)