Here are the items for the QA approach for i8 & i9

 

1.    The QA team will review the current JUnits-based unit testing approach; if needed, recommendations with be made.  There are concerns around the level of current inline comments in the code.

2.    The QA team will come up with a complete strategy for E2E testing for i8 & i9 that will focus on covering all the use cases.

3.    It is not clear if the QA team is responsible for doing an E2E test that represents a MASTER unit test. Is this needed?

4.    QA will address P1 and P2 items for i8 & i9. Please confirm that this is OK.

5.    Are there any other items that the QA team needs to address?

 