Team,

To help us firm up the project plan, we need each of you to come up with a high-level estimate of the effort for each of the i8 and i9 enhancements.  We would like to review these estimates during the F2F at 1:00 p.m. ET today.  Please add a comment to each enhancement and indicate one of the following estimates:

High - 2-3 days
Medium - 1 week
High - More than 1 week

See example: https://bugs.eclipse.org/bugs/show_bug.cgi?id=209244.  We realize that these may change once we get further in designs.  