Tania,
We
talked about this on the DC call today… Can we close off i8 BEFORE the (calendar)
year ends? Please follow up with Mark if you need further details, as
there are vacation considerations here.
Thanks,
Jimmy
Mohsin
+1-609-635-1703
From:
cosmos-dev-bounces@xxxxxxxxxxx [mailto:cosmos-dev-bounces@xxxxxxxxxxx] On
Behalf Of Tania N Makins
Sent: Tuesday, October 02, 2007 10:44 AM
To: cosmos-dev@xxxxxxxxxxx
Subject: [cosmos-dev] Vote Requested: Revised Schedule for COSMOS 1.0
COSMOS
Committers,
Please post
your vote for the revised COSMOS 1.0 Release Schedule:
http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.289.2F28.2F2007.29_-_Release_Milestones.
Tania
Tania N. Makins
Project Manager, AC Open Source Components
IBM Software Group - RTP, NC
Office: (919) 254-8430 T/L: 444-8430
tmakins@xxxxxxxxxx
-----
Forwarded by Tania N Makins/Durham/IBM on 10/02/2007 10:40 AM -----
Tania
N Makins/Durham/IBM@IBMUS
Sent by:
cosmos-dev-bounces@xxxxxxxxxxx
10/01/2007
03:59 PM
Please respond to
Cosmos Dev <cosmos-dev@xxxxxxxxxxx>
|
|
To
|
cosmos-dev@xxxxxxxxxxx
|
cc
|
|
Subject
|
[cosmos-dev]
Reminder - Proposal: Revised Schedule for COSMOS 1.0
|
|
So far, I have not seen any comments on the proposed schedule revisions. Remember
to post questions or comments today, so I can make revisions and post for a
vote tomorrow.
Tania
Tania N. Makins
Project Manager, AC Open Source Components
IBM Software Group - RTP, NC
Office: (919) 254-8430 T/L: 444-8430
tmakins@xxxxxxxxxx
----- Forwarded by Tania N Makins/Durham/IBM on 10/01/2007 03:56 PM -----
Tania
N Makins/Durham/IBM@IBMUS
Sent by: cosmos-dev-bounces@xxxxxxxxxxx
09/28/2007
06:42 PM
Please respond to
Cosmos Dev <cosmos-dev@xxxxxxxxxxx>
|
|
To
|
cosmos-dev@xxxxxxxxxxx
|
cc
|
|
Subject
|
[cosmos-dev]
Proposal: Revised Schedule for COSMOS 1.0
|
|
Team,
I have posted a proposal for a revised Milestone plan for COSMOS 1.0 on the
wiki, just below the current plan:
http://wiki.eclipse.org/Cosmos_Release_Plan#Proposed_Revisions_i7-i12_.289.2F28.2F2007.29_-_Release_Milestones.
The key changes to note in this proposal are:
- The start of i7 moves to Oct. 3
- Milestone 2 moves to Jan. 25 (the end of i8)
- Milestone 3 moves to Apr. 25 (the end of i10)
An alternative would be to:
- Set Milestone 2 for Nov. 28 (make the test pass for i7 2 weeks)
- Set Milestone 3 for March 7, just before EclipseCon (shorten the development
cycle for i9 to 4 weeks, make the test pass 2 weeks)
Please post your comments by end of day Monday. I will incorporate
feedback into the schedule, and post the revised schedule for a vote on Tuesday
morning.
Tania N. Makins
Project Manager, AC Open Source Components
IBM Software Group - RTP, NC
Office: (919) 254-8430 T/L: 444-8430
tmakins@xxxxxxxxxx_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev_______________________________________________
cosmos-dev mailing list
cosmos-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/cosmos-dev