I thought we had suggested keeping the Friday milestone date. This is the
date the milestone is declared. I really don't anticipate much happening
on the weekend. A Friday declaration would probably be more practical and
allow us to gain an extra weekend of user testing (who won't take it until
the milestone is declared).
[Derrick Keefe]
[Derrick Keefe] This date will represent the date that developers need to
have there features checked in. Setting a date for a "stable" build is less
definite as it will depend on the results of our testing and the ability to
turn around fixes. So it could be Wednesday, Thursday, Friday etc. The
important thing will be for us to declare a milestone build stable when it
is.
I would also suggest using the same numbers as Eclipse so that people know
which milestone we're lining up with. So that would put CDT 3.0 M5 on
March 11. We could use the Tuesday build on March 8 as the candidate with
rebuilds as necessary to meet our desired quality criteria by the Friday.
We can also consider going kamikaze and trying M5 the week before
EclipseCon.
[Derrick Keefe]
[Derrick Keefe] If people agree that this would be helpful, I'd be happy to
change this. BTW when we need to set milestones that do not line-up to
theirs, we could define milestones such as 5.2.
I'm not sure we need a milestone build before that. I don't think there's
been enough significant user-visible content at this stage to warrant it.
Eclipse 3.1 M4 is pretty early and it's quality shows so I'm not sure
there's much demand for a CDT build that runs against it. If people are
desperate, they can take a weekly build.
[Derrick Keefe]
[Derrick Keefe] I agree, so that's -2 for a February Build.
I'd be happy to debate this issue more, though.
Doug Schaefer
Ottawa Lab, IBM Rational Software Division
Derrick Keefe <dkeefe@xxxxxxx>
Sent by: cdt-dev-admin@xxxxxxxxxxx
02/06/2005 10:28 PM
Please respond to
cdt-dev
To
"'cdt-dev@xxxxxxxxxxx'" <cdt-dev@xxxxxxxxxxx>
cc
Subject
[cdt-dev] CDT 3.0 Milestones
Based on last weeks call, here are the purposed CDT 3.0 Milestone Dates in
relation to Eclipse 3.1. I'm not sure how useful a milestone build is
this
month (M1) please comment.
Eclipse 3.1 M4 based builds
CDT 3.0 M1 Monday, Feb. ? ,2005 - stable build reflecting progress.
Eclipse 3.1 M5 Feb 18,2005
CDT 3.0 M2 Monday, Mar.14 ,2005 - stable build reflecting progress
Eclipse 3.1 M6 Apr 1, 2005 API complete - API freeze
CDT 3.0 M3 Monday, April 11, 2005 - API freeze, stable build focus on
clearing bug backlog.
Eclipse 3.1 M7 May 13, stable build - feature complete - development
freeze
- lock down and testing begins
CDT 3.0 M4 Monday, May 30, 2005 - stable build, feature complete, RC0
Lock down and external testing begins with M4 and progresses through a
series of test-fix phases against candidate releases.
Release candidate builds are planned as follows (M4 is RC0)
Note these dates are conditional on Eclipse 3.1 schedule
CDT 3.0 RC1 Monday, June 13,2005 - Release Candidate
CDT 3.0 RC2 Monday, June 27, 2005 - Release Candidate
Eclipse 3.1 GA expected ~July 1
CDT 3.0 RC3 Monday, Jul. 18, 2005 - Release Candidate
_______________________________________________
cdt-dev mailing list
cdt-dev@xxxxxxxxxxx